Trainer profiles
- team
- design
- end
Drag the bars on a timeline; the dates in the text move with them.
Plan months of work on a timeline you can drag.
A timeline from a start and an end column, a lane per team, milestones, bars that fill with progress, the same work by quarter and on a board.
Members told us booking took eleven taps and a phone call. This quarter the timetable moves into the app, and booking takes three taps.
| task | team | status | end |
|---|---|---|---|
| Interviews | design | done | |
| Booking flow | design | done | |
| Class passes | design | doing | |
| Timetable service | backend | done | |
| Card payments | backend | doing | |
| Booking screen | app | done |
Payments come into the app, so a drop-in class is paid for as it is booked. Staff try it for six weeks before the public launch on 23 November.
| task | team | status | end |
|---|---|---|---|
| Trainer profiles | design | todo | |
| Waiting lists | backend | todo | |
| Pay at booking | app | doing | |
| Join a waiting list | app | todo | |
| Beta for staff | launch | todo | |
| Public launch | launch | todo |
Waiting lists fill the places people give up, and the first gym in Leeds opens with the app on day one.
| task | team | status | end |
|---|---|---|---|
| Live gym capacity | backend | todo | |
| Wallet passes | app | todo | |
| Bring a friend | launch | todo | |
| Open in Leeds | launch | todo |
todo 9
Trainer profiles
Waiting lists
Live gym capacity
Join a waiting list
Wallet passes
Beta for staff
Public launch
Bring a friend
Open in Leeds
doing 3
Class passes
Card payments
Pay at booking
done 4
Interviews
Booking flow
Timetable service
Booking screen
The timeline is one block of text: each piece of work is a line with a start and an end date.
as gantt by start to end draws each line as a bar between them, and group team gives each
team its own lane.
Public launch, launch, todo, 2026-11-23, , 0, is amilestone: one day, drawn as a diamond.
progress fills each bar that far.Each quarter's heading is a line such as ## Q4 2026 · Pay and launch. A rule of this page reads
the quarter out of it and sets it as a tag. The table under it is the same lines again,
filtered by their start date.
Push reminders, app, todo, 2027-02-15, 2027-03-12, 0. A new bar appears in theapp lane, and in the Q1 table.
group team from the block's first line. The lanes go, and the bars sit in one list.Next: Kanban board runs the day-to-day work; Project plan counts ticked boxes.
~~~ selfscribe
# Lesson: Plan months of work on a timeline you can drag.
# You learn: a timeline from a start and an end column, a lane per team, milestones, bars that fill with progress, the same work by quarter and on a board.
# Try this: drag the bar of "Card payments" two weeks later, and both its dates change in the text.
# Try this: change the progress of "Pay at booking" from 20 to 80, and its bar fills.
# summary: Drag the bars on a timeline; the dates in the text move with them.
# category: plans
# tags: interactive, simple, work
# uses: timeline, board
#
# ---- "```data NAME as gantt by START to END": a bar per line, from one date to the other --
# `use data` brings the Markdown rules plus data blocks and `view:` lines. `group team` gives
# each team a lane, and a line with a start and no end is a milestone.
use data
set title Product roadmap
set width full
set style sans
# ---- The colour of the chips and the quarter tags, with its shade for dark pages --------
palette
ink #0b7285 dark #66d9e8
# ---- "scope a · b · c" under the title: what the plan is for, cut into chips -----------
line scope _ -> div.rm-scope split "·" span.rm-chip { display: flex; flex-wrap: wrap; gap: 0.45em; margin: -0.5em 0 1.6em } as rm-scope
class rm-chip { font: 600 0.8em/1 var(--doc-font-ui); padding: 0.55em 0.9em; border-radius: 999px; background: color-mix(in srgb, var(--ink) 11%, transparent); color: var(--ink) }
class rm-chip:first-child { background: var(--ink); color: var(--doc-bg, #fff) }
# ---- "## Q3 2026 · …": a quarter's heading, with the quarter set as a tag before it ----
line ## Q_ · _ -> h2.rm-quarter _2 data-q=_1 { display: flex; align-items: baseline; gap: 0.6em; margin-top: 2em } as rm-quarter
class rm-quarter::before { content: "Q" attr(data-q); font: 700 0.62em/1 var(--doc-font-ui); letter-spacing: 0.06em; padding: 0.45em 0.7em; border-radius: 6px; color: var(--ink); border: 1.5px solid var(--ink) }
~~~
# Northside app: the road to spring
scope July 2026 to March 2027 · 4 teams · Goal: book a class in ten seconds
```data work as gantt by start to end group team plain
task, team:choice(design|backend|app|launch), status:choice(todo|doing|done), start:date, end:date, progress:number
Interviews, design, done, 2026-07-06, 2026-07-31, 100
Booking flow, design, done, 2026-08-03, 2026-09-04, 100
Class passes, design, doing, 2026-09-14, 2026-10-23, 60
Trainer profiles, design, todo, 2026-12-07, 2027-01-22, 0
Timetable service, backend, done, 2026-07-13, 2026-08-21, 100
Card payments, backend, doing, 2026-08-24, 2026-10-30, 45
Waiting lists, backend, todo, 2026-11-02, 2026-12-18, 0
Live gym capacity, backend, todo, 2027-01-11, 2027-03-05, 0
Booking screen, app, done, 2026-08-17, 2026-09-18, 100
Pay at booking, app, doing, 2026-10-05, 2026-11-20, 20
Join a waiting list, app, todo, 2026-12-07, 2027-01-29, 0
Wallet passes, app, todo, 2027-02-01, 2027-03-19, 0
Beta for staff, launch, todo, 2026-10-12, , 0
Public launch, launch, todo, 2026-11-23, , 0
Bring a friend, launch, todo, 2027-01-04, 2027-02-12, 0
Open in Leeds, launch, todo, 2027-03-15, , 0
```
## Q3 2026 · Book a class
Members told us booking took eleven taps and a phone call. This quarter the timetable moves
into the app, and booking takes three taps.
view: work as table columns task, team, status, end filter start < 2026-10-01 plain
## Q4 2026 · Pay and launch
Payments come into the app, so a drop-in class is paid for as it is booked. Staff try it for
six weeks before the public launch on 23 November.
view: work as table columns task, team, status, end filter start >= 2026-10-01 and start < 2027-01-01 plain
## Q1 2027 · Full classes and a second city
Waiting lists fill the places people give up, and the first gym in Leeds opens with the app on
day one.
view: work as table columns task, team, status, end filter start >= 2027-01-01 plain
## Where each piece stands
view: work as board by status columns task, team, end
## How it's made
The timeline is one block of text: each piece of work is a line with a start and an end date.
`as gantt by start to end` draws each line as a bar between them, and `group team` gives each
team its own lane.
- A line with a start and no end, such as `Public launch, launch, todo, 2026-11-23, , 0`, is a
milestone: one day, drawn as a diamond.
- A column called `progress` fills each bar that far.
- The status colours every bar, and the same colour follows it onto the board.
Each quarter's heading is a line such as `## Q4 2026 · Pay and launch`. A rule of this page reads
the quarter out of it and sets it as a tag. The table under it is the same lines again,
filtered by their start date.
## Try it yourself
1. Drag the bar of "Card payments" two weeks to the right. Both its dates change in the text.
2. Drag the right end of "Waiting lists" to make it shorter. Only its end date changes.
3. Change the progress of "Pay at booking" from 20 to 80. Its bar fills.
4. Add a line `Push reminders, app, todo, 2027-02-15, 2027-03-12, 0`. A new bar appears in the
app lane, and in the Q1 table.
5. Delete `group team` from the block's first line. The lanes go, and the bars sit in one list.
Next: *Kanban board* runs the day-to-day work; *Project plan* counts ticked boxes.