Board report

Status, risks, budget and decisions from short plain lines, laid out like a designed report.

Document · Advanced · uses chart, timeline, print

Edit it in the playgroundRead the file

What it shows

Write a board report from blocks that draw themselves.

What you learn

A title band, headline numbers, red-amber-green status, key facts beside the text, a cost bridge, a risk register with its heat map, a weighted choice, a roadmap, stages, an agenda and a sign-off.

Try this

  • Change Roof and solar panels: amber, slipping to Roof and solar panels: red, slipping, and its row and the bar above it turn red.
  • Change Bats return to the old block: unlikely, major to Bats return to the old block: likely, major, and its dot climbs the heat map.
examples/board-report.self · 195 lines
~~~ selfscribe
# Lesson: Write a board report from blocks that draw themselves.
# You learn: a title band, headline numbers, red-amber-green status, key facts beside the text, a cost bridge, a risk register with its heat map, a weighted choice, a roadmap, stages, an agenda and a sign-off.
# Try this: change `Roof and solar panels: amber, slipping` to `Roof and solar panels: red, slipping`, and its row and the bar above it turn red.
# Try this: change `Bats return to the old block: unlikely, major` to `Bats return to the old block: likely, major`, and its dot climbs the heat map.
# summary: Status, risks, budget and decisions from short plain lines, laid out like a designed report.
# category: writing
# tags: document, advanced, work
# uses: chart, timeline, print
use markdown
set title Board report
set page A4 portrait margins normal
# paper is the look; numbered numbers the ## headings, so the text can say "section 5".
set style paper numbered

# ---- Each block below is a plugin: you write a few plain lines, and it draws the picture.
# ---- ```cover``` a title: title, subtitle, then "Label: value" lines; "banner" sets it on a band.
block  ``` cover ... ```  -> cover  verbatim
# ---- ```stats``` headline tiles: "Name: value | change | note | trend".
block  ``` stats ... ```  -> stats  verbatim
# ---- ```status``` one workstream a line: "Name: green, amber or red | what is going on | owner".
block  ``` status ... ```  -> status  verbatim
# ---- ```facts``` a panel of "Label: value" facts; "aside" sets it beside the text.
block  ``` facts ... ```  -> facts  verbatim
# ---- ```waterfall``` a start, steps down and up, and "= Total" where they end.
block  ``` waterfall ... ```  -> waterfall  verbatim
# ---- ```risks``` "Risk: likelihood, impact | what is done | owner", with "->" for where it stands now.
block  ``` risks ... ```  -> risks  verbatim
# ---- ```score``` options scored against weighted criteria; "*" marks the one chosen.
block  ``` score ... ```  -> score  verbatim
# ---- ```horizons``` a roadmap: a heading ending in a colon starts a column, each line under it is a card.
block  ``` horizons ... ```  -> horizons  verbatim
# ---- ```steps``` a process in stages: "Name | what happens | how long".
block  ``` steps ... ```  -> steps  verbatim
# ---- ```agenda``` a meeting's items; each start time is worked out from "starts" and the lengths.
block  ``` agenda ... ```  -> agenda  verbatim
# ---- ```approvals``` who prepared, reviewed and approved: "Role: Name | title | date".
block  ``` approvals ... ```  -> approvals  verbatim
~~~
```cover
banner
New science and arts block
Hollins Park School · report to the Ashgrove Learning Trust board
Prepared by: Carver Allen, project managers
Date: 20 November 2026
Confidential
```

## Where the project stands

```stats
Spent to date: £1.92M | of £4.67M forecast | 0.21 0.58 1.07 1.48 1.92
Built: 41% | +17% | since September | 8 14 24 41
Contingency left: £184k | -£66k bad | of £250k
> Opening: September 2027 | on time
```

```status
Groundworks and drainage: done | handed over on 2 October | Pennine Build
Timber frame: green, improving | ground floor up; first floor from 30 November | Pennine Build
Roof and solar panels: amber, slipping | the panel supplier went into administration | Dan Whitlock
Heat pumps: amber, steady | grid connection date not yet confirmed | Aisha Rahman
Science labs: green | gas and fume cupboards designed and priced | Dan Whitlock
Planning conditions: green | bat survey signed off in October | Aisha Rahman
Moving classes in: not started | over the summer holiday 2027 | Joanne Hale
=> Two workstreams amber, none red. The board is asked to choose a second solar supplier (section 5).
```

## Summary

```facts
# At a glance
aside
School: Hollins Park, 1,140 pupils
Building: 6 labs, 4 art rooms, a gallery
> Contract: £4.60M | fixed price
Started: April 2026
Opens: September 2027
Contractor: Pennine Build
```

The frame is going up on time, and the school will open the new block in September 2027 as planned. The forecast cost is £4.67M, £66k over the contract sum. The trust's contingency covers it with £184k to spare.

One workstream needs the board. The supplier of the roof's solar panels went into administration in October, and the frame cannot be closed in without a roof. The board is asked to approve a second supplier (section 5) and to note the risks in section 4.

## The money

The contract sum is £4.60M at a fixed price. Changes since April are paid from the trust's contingency of £250k.

```waterfall
# Where the contingency has gone
Contingency at the start: £250k
Poor ground under the art rooms: -£72k
Bat boxes and a later demolition: -£18k
Cheaper cladding, same look: +£55k
> Second solar supplier: -£31k | if the board approves it
= Left
```

## Risks

Two risks have come down since September because of work already paid for. The grid connection is the one to watch: without it the heat pumps cannot run.

```risks
Solar panels arrive late: likely, major -> possible, minor | second supplier, see section 5 | Dan Whitlock
Grid connection comes after opening: possible, severe | a hired boiler is priced as a fallback | Aisha Rahman
Winter weather stops the frame: likely, moderate | frame wrapped; two weeks of float in the plan | Pennine Build
Bats return to the old block: unlikely, major -> rare, major | bat boxes up; demolition outside the roosting season | Aisha Rahman
Lab gas fails its first inspection: rare, severe | specialist checks at first fix | Dan Whitlock
Complaints from Coppice Lane: likely, minor | no deliveries before 8 am; a letter to every house | Joanne Hale
```

## Choosing a second solar supplier

Three firms quoted. Delivery matters most: the roof has to be closed by March, or the fit-out moves into the summer and the opening slips.

```score
| *Brightwell Solar | Northgate Energy | Sunfield UK
Price (weight 2): 3 | 5 | 4
Delivery by February (weight 4): 5 | 2 | 4
Warranty (weight 3): 5 | 3 | 4
Has fitted school roofs before (weight 2): 5 | 2 | 3
=> Brightwell Solar: the only one with panels in stock in the UK, and a 25-year warranty.
```

## The plan from here

```horizons
Autumn 2026:
[x] Groundworks and drainage
[>] Timber frame | Pennine Build
[>] Choose a solar supplier | for decision on 3 December
Spring 2027:
Roof, panels and windows | closed in by March
Heat pumps and labs, first fix
Summer 2027:
Fit-out and furniture
Move classes in | over the holiday | Joanne Hale
September 2027:
Open to pupils | 6 September
```

How the school moves in, once the contractor hands over:

```steps
Pack | each department boxes its rooms in the last week of term | 1 week
Hand over | keys, safety files and a walk round with the contractor | 22 July
Move | removals over two weekends, the labs last | 2 weeks
Set up | computers, gas checks and a fire drill with staff | 1 week
```

## The next meeting

```agenda
# Trust board, 3 December 2026
starts 16:00
Welcome and apologies | Chair | 5 min
This report | Dan Whitlock | 20 min
> Second solar supplier | Dan Whitlock | 15 min | for decision
Risks and the grid connection | Aisha Rahman | 15 min
Break | 10 min
Moving classes in | Joanne Hale | 15 min
Any other business | 10 min
```

## Sign-off

```approvals
Prepared by: Dan Whitlock | Project manager, Carver Allen | 18 November 2026
Reviewed by: Aisha Rahman | Estates director, Ashgrove Learning Trust | 19 November 2026
Approved by: Joanne Hale | Head teacher, Hollins Park
Received by: | Chair of the trust board
```

---page---

# About this example

## How it's made

Every picture in this report is a few plain lines in a fenced block, and a rule in the rules block names the plugin that draws it. The status table is seven lines, and the heat map six.

Change a word like `amber` or `likely`, and the picture follows. Open the Source to see each block next to what it draws.

`set style paper numbered` gives the sheet and numbers the `##` headings, so the text can point to "section 5". The `#` heading above starts the numbers again.

## Try it yourself

1. Write `= Left: £184k` in place of `= Left` in the money block. The block checks the sum and says it matches.
2. In the supplier scores, move the `*` from Brightwell Solar to Sunfield UK. The block says Sunfield is chosen, though Brightwell scores higher.
3. In the agenda, change the `20 min` after `This report` to `30 min`. Every start time after it moves on ten minutes.
4. Put `[x]` before `Pack` in the moving-in stages. Its disc fills with a tick, and the stages after it show as still to come.
5. Add `2 December 2026` after `Head teacher, Hollins Park` in the sign-off. That slot shows as signed.

Next: *Printable checklist* prints a form to fill in with a pen; *Sales dashboard* draws its charts from a list of orders.